In
a recent case of contractual damages between North Sydney Leagues'
Club Ltd v Synergy Protection Agency Pty Ltd [2010] NSWSC 256, the
Court held that fixed overhead costs should be taken into account in
determining net profit in calculating expectation damages.
ISSUES
1) What
are Expectation Damages? These damages aim to restore the aggrieved
party in a position where the damage had not occurred.
2) It
is not disputed that when assessing loss of profits, the difference
between revenue and costs is to be taken into account.
3) However,
are fixed costs a part of the above equation?
4) If
fixed costs are included, the overall costs would logically increase
and subsequently the profit would also decrease.
COURT’S
FINDINGS
Assessing
damages is left up to the court’s discretion. It usually tends to
follow one of two assessment basis - expectation damages and reliance
damages.
Reliance
damages allow the wronged party to recover damages on the basis that
it would not have incurred but for the breach of the contract.
Unfortunately, Syngery only pleaded one basis and did not make room
for an alternative. The court held that Synergy should have made room
for a second basis.
How
then are fixed overhead costs calculated?
Dart
Industries Inc v Décor Corporation Pty Ltd (1993) 179 CLR 101
provides guidance on this evidentiary question. As per this case,
factors taken into account included whether the overheads were
increased by the sale of the product; whether they reflected costs
which would have decreased; whether they reflected costs which would
have inevitably accrued; or whether there was surplus capacity.
In
essence, courts pay attention to the nature of the costs and their
connection to the contract.
LESSONS
1) It
is advisable to consider all bases before seeking damages – a
backup option will not hurt.
2) The
good news is that overhead fixed costs are recoverable although
within bounds.
3) This
depends on whether these types of costs are extra costs indeed or
losses.
4) Courts
will restore parties in the position before the damage occurred or if
the damage had not occurred but it will not put the party in a better
position had the contract been performed.